North End Water and Sewer Works May 2017 Update

The May 2017 work plan by Boston Water & Sewer Commission is shown below as part of Phase II of the multi-year North End Water, Sewer and Drainage Project.

During May, work will continue on Hanover Avenue and Hull Street, with a new water main installation beginning on Richmond Street. This month also brings hope of several project completions on Hanover Street, Hull Street, Snow Hill Street, Sheafe Street and parts of North Street.

See below for scheduling details and contact information. The second page explains all remaining work with a projected time.