North End Water & Sewer Works Oct. 2020 Update: New Hydrants for Fulton St.; Work Continues on Battery St., Cleveland Pl., & Commercial Wharf N.

The October 2020 work plan by Boston Water & Sewer Commission is shown below. In September, sewer pipes were replaced on Margaret St. and Battery St., and sewer lines were lined on Commercial Wharf N., and Cleveland Pl. In October, residents can expect to see work continue on Battery St., Cleveland Pl., and Commercial Wharf N., as Read More…

Featured Health & Environment

North End Water & Sewer Works Sept. 2020 Update: Work Continues on Tileston St., Margaret St., & Battery St.

The September 2020 work plan by Boston Water & Sewer Commission is shown below. In August, sewer pipes were replaced on Tileston, Margaret, and Battery Streets. Water mains were also replaced on Tileston and Battery Streets. Work will continue on these streets in September, with some disruptions on Cleveland Place as well. See below for more details Read More…

Featured Health & Environment

North End Water & Sewer Works Aug. 2020 Update: Work Starts on Battery St. & Commercial Wharf N., Continues on Tileston St. & Margaret St.

The August 2020 work plan by Boston Water & Sewer Commission is shown below. In July, water & sewer main work was completed on Lewis St. and pipes were replaced on Tileston and Margaret Streets. In August, work will begin on Battery St. and Commercial Wharf North. Expect replacement of water and sewer mains to continue on Read More…

Featured Health & Environment

North End Water And Sewer Works July 2020 Update: Work Continues on Tileston St. & Lewis St., New Projects Begin on Margaret St. & Cleveland Pl.

The July 2020 work plan by Boston Water & Sewer Commission is shown below. In June, water main work was completed on parts of Lewis and Tileston Streets. In July, expect work on Lewis and Tileston Streets to continue, as well as new work to start on Margaret Street and Cleveland Place. See below for Read More…

Health & Environment Transportation

North End Water and Sewer Works July 2018 Update

The July 2018 work plan by Boston Water & Sewer Commission is shown below as part of the multi-year North End Water, Sewer and Drainage Project. In June, water main work was completed on Cross Street. During July, work will begin on a bypass installation on Blackstone Street. See below for more details and project contact Read More…

Meetings

Next Phase Starting for North End Water, Sewer and Drainage Project

Irene McSweeney from Boston Water and Sewer Commission (BWSC) presented an update on the North End improvements project at the April North End / Waterfront Neighborhood Council (NEWNC) meeting. Work on phase 3 of these improvements will begin this spring. The BWSC will send out monthly updates to the community as project details unfold. Watch Read More…

Health & Environment Transportation

North End Water and Sewer Works December 2017 Update

The December 2017 work plan by Boston Water & Sewer Commission (BWSC) is shown below as part of Phase II of the multi-year North End Water, Sewer and Drainage Project. Water main installation was completed on Baldwin Place and Jerusalem Place in November. Upcoming work will take place on North Street and Sheafe Street as Read More…

Health & Environment Transportation

North End Water and Sewer Works November 2017 Update

The November 2017 work plan by Boston Water & Sewer Commission is shown below as part of Phase II of the multi-year North End Water, Sewer and Drainage Project. October saw the completion of work on Richmond Street! During November, work will continue on North Street and Snow Hill Street. New construction is scheduled to Read More…

Health & Environment Transportation

North End Water and Sewer Works October 2017 Update

The October 2017 work plan by Boston Water & Sewer Commission is shown below as part of Phase II of the multi-year North End Water, Sewer and Drainage Project. During October, work will continue on North Street, Richmond Street and Snow Hill Street. New construction will begin on Baldwin Place and Jerusalem Place. See below Read More…

Health & Environment Transportation

North End Water and Sewer Works September 2017 Update

The September 2017 work plan by Boston Water & Sewer Commission is shown below as part of Phase II of the multi-year North End Water, Sewer and Drainage Project. During September, work will continue on North Street, Richmond Street and Snow Hill Street. New construction will begin on Baldwin Place and Jerusalem Place. See below Read More…

Featured Health & Environment

North End Water and Sewer Works August 2017 Update

The August 2017 work plan by Boston Water & Sewer Commission is shown below as part of Phase II of the multi-year North End Water, Sewer and Drainage Project. The end of July saw the end of work on Hanover Avenue and Sun Court Street, hooray! During August, work will continue on North Street, Richmond Read More…

Health & Environment

North End Water and Sewer Works July 2017 Update

The July 2017 work plan by Boston Water & Sewer Commission is shown below as part of Phase II of the multi-year North End Water, Sewer and Drainage Project. During July, work will continue on Hanover Avenue, Richmond Street and Snow Hill Street. New construction will begin on Sun Court Street. See below for scheduling Read More…