The North End/Waterfront Residents’ Association voted 43-0 in support of a headhouse modification at 105 Prince Street. The condominium association is seeking zoning relief to rebuild and expand the headhouse on the roof of the 5-story residential building.
The headhouse and surrounding roof area had leak and drainage issues. Their contractor intends to add 2 steps which will raise the height of the headhouse by approximately 3 feet.
An abutter at 109 Prince St supported the change subject to a raised curb on their side. The condo association agreed to work out this issue with abutter and provide new drawings.
The ZBA hearing on this issue is Tues., 9/15 at City Hall. See the Calendar for details.
105 Prince St., Condominium Association has filed an appeal seeking zoning relief to rebuild and expand the headhouse on the roof of the 5-story residential building.
Headhouse and surrounding roof area had leak and drainage issues.
Needed to add 2 steps and therefore change the door which raised the height of the headhouse.
Water drainage will be away from the party wall.
ZBA hearing is Tues., 9/15 at City Hall
Abutter at 109 Prince St – is agreeable to the variance subject to a raised curb on their side
Condo association agreed to work out this issue with abutter and provide new drawings.
Vote: 43 Support, 0 Oppose – NEWRA supports the application