Boston Water & Sewer Commission (BWSC) is providing the following update and schedule for the major sewer and water main project underway in the North End.
In October 2015, a new water main, storm drain and combined sewer were completed on Hanover Street, between Charter and Commercial Street.
Coming in November 2015, BWSC will be working on Battery Street to install a structural liner of the combined sewer line. Also, on Hanover Street, there will be completion work.
The BWSC North End project will continue through 2016. Contact numbers are included below for residents and businesses that have questions or concerns.