Below is the construction look ahead for the North Washington Street Bridge Replacement Project as provided by the Massachusetts Department of Transportation (MassDOT) for August 25 – September 7.

Travel Impacts

  • Inbound: One of two lanes open and all turn movements available from 10 a.m.–2 p.m. on some weekdays.
  • Outbound: One of two lanes open and all turn movements available from 7 a.m.–2 p.m. on some weekdays.
  • No work or lane closures on the bridge will take place on Monday, September 2 in observance of Labor Day.

Paul Revere Park Playground

DESCRIPTION: Installation of new playground equipment will continue in Paul Revere Park.
WORK HOURS: Daytime (7 a.m. – 3 p.m.) on weekdays.

Temporary Bridge Construction

DESCRIPTION: Construction will continue on the temporary vehicle, pedestrian, and utility bridges including installation of pipes, joints, and bridge spans. 
WORK HOURS: Daytime (6 a.m. – 3 p.m.) on weekdays.