Event Notices Health & Environment

Salem Street Repaving Starts Tuesday, October 15th; More North End Streets in November

ATTENTION:

BOSTON PUBLIC WORKS WILL BE RESURFACING

SALEM STREET

CROSS STREET TO CHARTER STREET

BEGINNING

TUESDAY OCTOBER 15, 2013

BETWEEN THE HOURS of 7:00 A.M. AND 3:30 P.M.

THE CONSTRUCTION WILL BE COMPLETED IN THE FOLLOWING PHASES
AND WILL TAKE APPROXIMATELY 10-14 DAYS:

  • PHASE 1: THE EXISTING ROADWAY WILL BE SCARIFIED

(THIS PROCESS WILL EXPOSE EXISTING ROADWAY STRUCTURES TO A HEIGHT OF 1.5 INCHES – PLEASE USE CAUTION WHILE DRIVING)

  • PHASE 2: ROADWAY STRUCTURES WILL BE ADJUSTED TO CORRECT HEIGHT OR REPLACED AS NEEDED
  • PHASE 3: ROADWAY WILL BE FINISH PAVED

NOTE:  PLEASE OBSERVE POSTED SIGNS FOR PARKING RESTRICTIONS.

CARS PARKED IN POSTED AREAS WILL BE TOWED.

THE CITY OF BOSTON UNDERSTANDS THE INCONVENIENCE THAT THIS WORK CAUSES.  HOWEVER, THE CONSTRUCTION IS DEEMED NECESSARY AND WILL GREATLY IMPROVE THE QUALITY OF THE STREET.

PLEASE BE PATIENT WITH US UNTIL THE WORK IS COMPLETED.

THANK YOU.

ANY QUESTIONS?  CALL 617-635-4950.

[hr]

List of North End Streets that will be paved by mid-November:

North End BATTERY ST HANOVER ST COMMERCIAL ST 310 33 RESURFACE
North End FOSTER ST CHARTER ST COMMERCIAL ST 210 10 RESURFACE
North End SALEM ST CROSS ST CHARTER ST 1514 17 RESURFACE
North End GREENOUGH LN CHARTER ST COMMERCIAL ST 115 6 PATCH ALLEY