The majority of the sewers on various streets in the North End have been cleaned and televised to determine their condition. A section of the Commercial St. (Atlantic Ave.) sewer between Cross and Richmond Streets will be lined the week of March 19, 2012. The work is expected to take 3 to 5 days to complete. Access to the sewer system may necessitate a reduction in available parking spaces. Separate notices will be delivered to impacted customers. Call Mr. Bang Nguyen, Project Engineer at (617) 989-7460 with questions.
Related Articles
May 2015 Schedule for North End Sewer Project
Boston Water & Sewer Commission has issued the following schedule and update on the major North End Project with water main replacement and sewer rehabilitation. Significant work will occur this month on Hanover Street and Harris Street, as well as surrounding intersections. See the update below for details and contact information.
North End Water and Sewer Work February 2017 Update
The February 2017 work plan by Boston Water & Sewer Commission is shown below as part of Phase II of the multi-year North End Water, Sewer and Drainage Project. Contact information and scheduling for the upcoming month of construction are included. The second page details all remaining work with a projected timeline.
North End Water and Sewer Works October 2017 Update
The October 2017 work plan by Boston Water & Sewer Commission is shown below as part of Phase II of the multi-year North End Water, Sewer and Drainage Project. During October, work will continue on North Street, Richmond Street and Snow Hill Street. New construction will begin on Baldwin Place and Jerusalem Place. See below Read More…