Below is the construction look ahead for the North Washington Street Bridge Replacement Project as provided by the Massachusetts Department of Transportation (MassDOT).
Travel Impacts
- Inbound: one lane available on weekdays off-peak, 10 a.m. – 2 p.m.
- Keany Sq. inbound: two lanes and all turn movements available overnight, 7 p.m. – 5 a.m.
- Keany Sq. outbound: one lane and all turn movements available on weekdays off-peak, 7 a.m. – 2 p.m.
- Tudor Wharf walkway: occasional daytime closures with detour access via Water Street underpass
Night Work
Description: At Keany Square, test pit digging for a future drainage line will begin Monday, July 15 and is expected to be completed by July 27.
Work Hours: Overnight (7 p.m. – 5 a.m.), Monday nights through Saturday mornings.
Paul Revere Park Playground
Description: Delivery and installation of new playground equipment will begin in Paul Revere Park.
Work Hours: Daytime (7 a.m. – 3 p.m.) on weekdays.
Temporary Bridge Construction
Description: Continued construction of the temporary vehicle, pedestrian, and utility bridges including bridge bents, abutments, and utilities.
Work Hours: Daytime (6 a.m. – 4 p.m.) on weekdays and Saturday, July 20.
Utility Installations & Upgrades
Description: Continued installation of a waterline by J.F. White and a gas pipe by National Grid at Keany Square.
Work Hours: Daytime (7 a.m. – 3 p.m.) on weekdays.
Read more from MassDOT here and follow NorthEndWaterfront.com coverage of the bridge project by searching the tag N. Washington St. Bridge.